HS2 tunnel link reaches Old Oak Common: what this construction milestone means

The latest announcement concerns the station’s connection to the tunnels from the west. Here is what has been built and why it does not mean trains are starting to run.

HS2 announced on 4 November that a tunnel connection had broken through into the Old Oak Common station under construction. This created a continuous underground link to the portal at West Ruislip. It is news about construction progress, not the opening of a passenger service. In the same announcement, HS2’s chief executive described opening the route to Birmingham in 2037 or earlier as a challenging ambition, rather than a confirmed start date for services.

Why did the final section require different work from the long tunnel? As transport website ianVisits explains, space is needed near the station for trains to move between tracks leading to the platforms. Work on the connecting sections began from Victoria Road in May 2024. The two 360-metre sections were mined through London clay using excavators, rather than a large tunnel boring machine. A sprayed-concrete lining was followed by concrete cast using travelling formwork.

That distinction helps explain why finishing excavation does not mean completing the railway. In a separate notice for Hillingdon and Ealing, updated on 20 August, HS2 described further work inside the Northolt tunnel: building emergency and maintenance walkways and fitting out passages between the parallel tunnels. These connections, spaced approximately 500 metres apart, are intended to allow passengers to move into the other bore in an emergency. The August plan scheduled work until late autumn; it does not confirm that the work is complete today.

Interchange arrangements will also matter to future passengers. An announcement on 29 September confirmed agreement on a design providing level boarding for Elizabeth line trains at their usual platforms, numbered 5–8. It is intended to reduce the need for ramps and staff assistance for many passengers with reduced mobility. There is an important qualification: level boarding will be available when a train uses its usual platform. This is not a promise of identical boarding conditions under every possible platform allocation.

The project involves more than new tunnels. HS2’s Old Oak and North Acton information page describes railway bridge alterations, utility diversions and lowering Old Oak Common Lane so double-decker buses can pass beneath the new structures. A cycle route and pedestrian paths protected by barriers are planned alongside the carriageway. These are elements of the station’s surrounding infrastructure, not changes announced for the first time in November.

Residents following the impact on their street can use the official works map, searching by postcode or place name, and the construction updates for Old Oak and North Acton. Questions about the work can be directed to the HS2 team on 08081 434 434. It is therefore useful to read construction milestone announcements separately from notices about specific neighbourhood works: they answer different questions.